10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

The CxA exam has 125 questions and runs 4 hours 15 minutes.

These 10 free CxA questions are organized by exam domain, so you can see how each part of the Certified Commissioning Authority blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Managing Commissioning Projects 18% of exam

Question 1

Friday's commissioning visit includes full functional testing of two independent air-handling systems. AHU-East has completed startup, controls checkout, calibration, and TAB. AHU-West still lacks TAB. The approved plan permits separate testing, and there are no shared interlocks, outage constraints, or unresolved hazards affecting East. The contractor asks to postpone the entire visit. The CxA should revise the schedule to:

Show answer & explanation

Correct answer: D - Test East as scheduled and defer West's airflow-dependent tests until its readiness is established.

Question 2

A value-engineering proposal would delete a chiller's permanent water-flow meter. The owner's project requirements call for continuous kW/ton reporting across the operating-load range. Electrical input and entering/leaving water temperatures will still be measured. The pump has variable-speed control, but the proposal assumes the design flow confirmed during TAB whenever the chiller runs. Which response preserves the required function?

Show answer & explanation

Correct answer: C - Retain a verified means of measuring operating flow for the required kW/ton calculation.

Domain 2: Preparing Commissioning Documentation 19% of exam

Question 3

The approved sequence requires a standby chilled-water pump to restore at least 95 gpm within 15 seconds of lead-pump failure and generate a BAS alarm. A draft functional test simply forces the standby pump ON and checks motor rotation. Safe fault simulation and system restoration procedures are already approved. Which replacement step would test the automatic failover function?

Show answer & explanation

Correct answer: A - Trip the lead pump by the approved method while demand remains active; record automatic standby flow recovery and alarm timing.

Domain 3: Conducting Commissioning Activities 24% of exam

Question 4

During a power-loss test, the generator and automatic transfer switch complete their specified sequence, with transfer in 9 seconds against a 12-second limit. A separately specified uninterruptible power supply (UPS) must keep the network rack continuously energized throughout the event. A recorder at that rack detects a 0.8-second loss of voltage, and the servers restart. Which acceptance conclusion is supported without assuming a root cause?

Show answer & explanation

Correct answer: B - The source-transfer requirement passes; the protected-load continuity requirement fails.

Question 5

While investigating an AHU acceptance-test failure, a mechanic removes the belt guard after the fan has been stopped through the BAS. The fan is stationary, but its variable-frequency drive remains energized and automatic restart is enabled. The mechanic reaches toward the belt. What must the CxA do immediately?

Show answer & explanation

Correct answer: A - Stop the adjustment until authorized personnel isolate hazardous energy and verify the safe state.

Question 6

A VAV terminal is holding a displayed airflow of 900 cfm at its 900-cfm setpoint, yet a calibrated duct traverse measures 600 cfm. The controller's differential-pressure input agrees with a reference manometer, and the manufacturer's correct pickup relationship also gives 600 cfm. There is no intervening duct leakage, and inlet pressure is adequate. Before changing the fan pressure or terminal setpoint, where should the CxA focus the correction?

Show answer & explanation

Correct answer: B - The controller's pressure-to-airflow scaling, followed by a repeat airflow-control test.

Domain 4: Managing Training Activities 4% of exam

Question 7

Everyone attended the chilled-water plant training. During supervised recovery exercises, two night-shift operators cannot identify the pump-flow permissive needed before a chiller restart. The other required tasks have been demonstrated successfully. The contract requires each operator to demonstrate plant recovery, not merely attend instruction. The training follow-up should be to:

Show answer & explanation

Correct answer: D - Retrain the two operators on the recovery sequence and repeat their observed demonstration.

Domain 6: Conducting Existing Building Commissioning 23% of exam

Question 8

An office AHU cannot maintain its 55°F supply-air setpoint. After 30 minutes of steady operation, calibrated probes read 55°F immediately after the cooling coil and 64°F after the downstream hot-water coil. The heating command is 0%, and the actuator is at its closed stop. The fan is upstream of both probes; there is no other heat source between them. Which fault should lead the investigation?

Show answer & explanation

Correct answer: C - Hot-water flow through the nominally closed heating valve.

Question 9

An existing AHU is undergoing an authorized minimum-outdoor-air test at 10,000 cfm total supply flow. Simultaneous calibrated readings are: return air 78°F, outdoor air 38°F, mixed air before the coils 70°F, and supply air after the active cooling coil 55°F. Mixing is complete, air-density differences are negligible, and no heat is added or removed before the mixed-air measurement. The required outdoor airflow is at least 2,500 cfm. What does the temperature-mixing calculation indicate?

Show answer & explanation

Correct answer: D - 2,000 cfm; it falls below the required outdoor airflow.

Question 10

"The room matches the original drawings, but every evening class complains," says a facilities manager. A former eight-person office now accommodates 40 trainees until 9 p.m.; the original HVAC schedule ends at 6 p.m. Original commissioning and TAB records are complete, but no requirements have been established for the changed use. What should anchor the existing-building commissioning investigation?

Show answer & explanation

Correct answer: B - Current facility requirements covering classroom occupancy, ventilation needs, and the evening operating schedule.

The rest of the CxA blueprint

The CxA exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more CxA questions with explanations.

Continue in the free practice test →